The latest confirmed movement, the open question and the next checkpoint.
OPENCounty Road 1 / Farmstead infrastructure
The Town says LGI Homes is in default of its development agreement over delayed infrastructure work.
Still unresolved: Completion and reopening of County Road 1 and the roundabout, plus any additional Town enforcement or legal action.
Next checkpoint: A Town notice of reopening, completion or further action.
Town update September 16.
OPENBerthoud Main Street strategic planning
The Town committed $50,000 to the partnership and Berthoud Main Street plans a DOLA-supported strategic workshop this fall.
Still unresolved: The resulting 3-to-5-year downtown strategic plan, annual work plan and priorities for the program area.
Next checkpoint: The strategic workshop and an adopted downtown work plan.
Town partnership approved August 11.
OPENUrsa Major Colorado expansion
The Berthoud-headquartered aerospace company opened a Longmont site in August for its avionics and in-space propulsion teams and some corporate staff, and says it is clearing floor space at its Berthoud headquarters for more manufacturing.
Still unresolved: How many of the up to 1,800 new jobs the expansion may add will be at the Berthoud headquarters.
Next checkpoint: A company or Town update identifying Berthoud jobs and investment.
Longmont facility opening August 20.
OPEN2026 Town strategic plan implementation
The approved strategic plan identifies Economic Development, Communications & Transparency, and Financial Stability as high-level objectives through March 2028.
Still unresolved: The specific actions, measures and public results that will demonstrate progress on each objective.
Next checkpoint: Published implementation measures and Board progress reports.
Plan approved September 8.
OPENLarge data centers
Trustees adopted Ordinance 1391, which temporarily suspends the acceptance, processing and approval of applications for large data centers, on September 22 in a 5-2 roll call vote, with Trustees Wing and Olbricht dissenting, according to the meeting minutes. The minutes say discussion focused on the size threshold for a large data center. The Board's September 29 study-session agenda listed an initial discussion of land-use considerations for data centers.
Still unresolved: Permanent siting, infrastructure and process rules.
Next checkpoint: A draft ordinance or Board action on permanent rules.
The September 22 minutes, approved October 13, record a 5-2 vote on the moratorium.
OPENWelch Avenue drainage redesign
Proposals are due October 23 for engineering and construction-document services.
Still unresolved: Firm selection, final design, cost and construction schedule.
Next checkpoint: October 23 proposal deadline and a consultant award.
Design RFP posted September 23.
OPENJaskowski Open Space
Town Administrator Chris Kirk's September 23 memo to trustees says the Town received several bids for the Jaskowski improvements project, all close to the expected budget, and that the bids will be brought to the Board in October.
Still unresolved: Bid results, contract award and construction timing.
Next checkpoint: Board consideration of the bids, expected in October.
OPENWater-efficiency plan
Public feedback remains scheduled through October 26. The town's draft goal is to reduce use from 109 to 105 gallons per person per day by 2032.
Still unresolved: Final revisions and formal adoption.
Next checkpoint: October 26 close of comments, followed by adoption proceedings.
OPENHeron Lakes Marina / 22nd Filing
Trustees continued the public hearing on Resolution 2026-25, the neighborhood master plan for Heron Lakes Marina (22nd Filing), to October 27 in a 5-1 roll call vote, with Mayor Pro-Tem Soricelli-Albrecht dissenting and Trustee Murphy abstaining. The September 22 minutes say trustees discussed the property's water provider and expressed concerns about the metro district. The Planning Commission had recommended approval on the condition that the water provider be determined and provided with the preliminary plat.
Still unresolved: Approval, denial or conditions for the neighborhood master plan.
Next checkpoint: The continued public hearing October 27.
The September 22 minutes record the 5-1 vote to continue the hearing to October 27.
OPENBerthoud Veterans Club funding request
Trustees approved $11,500 for the Berthoud Veterans Club on September 22 in a 7-0 roll call vote. The minutes say representatives of the American Legion and the Veterans of Foreign Wars sought the money to help with rent for the organization's building, and trustees encouraged the group to pursue fundraising.
Still unresolved: Whether the $11,500 covers the club's rent for the full year, a question trustees raised at the meeting.
Next checkpoint: Any further funding request from the club.
The September 22 minutes record the 7-0 vote.
OPENMcCarty property matter
The September 22 minutes record a 7-0 vote to go into executive session on the potential acquisition of the McCarty property. The minutes record no public action on the matter.
Still unresolved: Any later public action or disclosed disposition.
Next checkpoint: Public minutes or subsequent Board action.
The September 22 minutes record the executive session and no public action.
OPENUNCONFIRMEDEngineering Supervisor hiring
Not confirmed against the source as of October 19, 2026: that applications closed October 14 at 5 p.m. (the posting is no longer on the Town's jobs page, so the closing date and time could not be checked). Check the source before relying on it.
Applications for the development-review supervisor position closed October 14 at 5 p.m. The position no longer appears among the Town's open full-time jobs, and no hire has been announced.
Still unresolved: The hiring outcome.
Next checkpoint: A Town announcement of the hire.
Applications closed October 14.
AWAITING RECORDSSeptember 29 Board study session
The Town streamed the September 29 study session live on its YouTube channel, where the recording remains available. The agenda listed four discussion topics: land-use considerations for data centers, a capital improvements program manual, proposed purchasing-policy updates and Board meeting procedures. No minutes have been posted in the Town's agenda portal.
Still unresolved: Written minutes and any next steps from the discussion.
Next checkpoint: Minutes or a future action agenda.
The Town streamed the study session live on YouTube September 29.